Choosing an approach
Wingate (2025, p. 54) links the choice of method to the work: experience with the methods favours a traditional plan, while higher ambiguity makes a flexible, Agile approach "more applicable". My project has both kinds of work. The deadlines and the order of key steps are fixed: ethics approval comes before any data, and the measurement harness must pass a pilot before the main run. Building the advisor is more exploratory, so I will build it in three increments. That points to a hybrid: a fixed plan for milestones and a flexible board for the work between them.
Breaking the project down
Week 2 was about decomposition: splitting one large goal into pieces small enough to plan and track. My six objectives are the top level. Under the advisor objective sit its three increments: a variant generator, a build-and-scan orchestrator and a report generator. Each of these splits into tasks of a day or less. Phelps, Fisher and Ellis (2007, p. 84) define a milestone as "a significant event, outcome or 'deliverable' that has a set date" and suggest working backwards from each one. My milestones are the completion checks already written into my objectives.
| Objective | Completion check (milestone) |
|---|---|
| O1 Ethics self-assessment approved | Before any data collection (gate) |
| O2 Measurement harness built | Pilot detects a deliberately unrecorded library (gate) |
| O3 Measure all 15 images | Scanner misses reported to maintainers |
| O4 Judge H1, H2a, H2b | Once every image is measured |
| O5 Evaluate the advisor | 5 held-out Dockerfiles vs always-Slim |
| O6 Release guidance, dataset and tool | By the end of the project |
The Kanban board
I will run a Kanban board in GitHub Projects with three columns: To do, In progress and Done. Each research phase, from planning and ethics through build, pilot, measurement and analysis to release, is its own row across those columns, and the two gates are marked. I chose GitHub Projects because the board sits beside the code, scripts and results, so each card can link to the commit that finished it. Wilson et al. (2017) recommend using an issue tracker as the to-do list and keeping a dated change log; I will do both. I will allow only two task cards in progress at once, because I work full time alongside the project. The two standing cards, the weekly review and the integrity log, sit outside that limit. Across the 23 studies in a mapping study of Kanban in software engineering, the benefit reported most often was better visibility and transparency of work (Ahmad et al., 2018, p. 105). Most of that evidence comes from teams, not individuals, so for a solo project it is a reasonable expectation rather than a proven result.
I considered three alternatives. Jira is built for teams, and its workflows, permissions and sprint ceremonies would add overhead a solo project does not need. Trello is simpler, but on its free plan, without add-ons, it has no timeline view and does not link cards to commits; both need a paid plan or a Power-Up. A spreadsheet Gantt is quick to draw but drifts from the real task list as soon as plans change. GitHub Projects has one weakness that matters here: its roadmap has no dependency arrows, so the ethics and pilot gates are dated milestones that I check at each weekly review, not links the tool enforces.
The Gantt chart
The Gantt chart is a timeline view of the same GitHub project, so the board and the schedule never drift apart. Every card has a start and a target date, so the roadmap shows each research phase over time and marks the two gates. The research itself is planned from 12 January to 28 February 2027. I don't know the exact PROM06 submission date yet, so I plan to finish at the end of February to be safe, and the last five days are kept free. That is about 10% slack, the low end of the 10 to 30% that Phelps, Fisher and Ellis (2007, p. 84) advise. Tools only go so far: project management software "does not manage the project for you and does not substitute for sound planning" (Phelps, Fisher and Ellis, 2007, p. 87). So the gates are written into the plan first, then drawn on the chart. Hours per task come in Assignment 2. Together the two views work at two levels: the board gives the at-a-glance view of what is blocked today, and the roadmap gives the deeper view of whether the gates are drifting.
The risk register
My proposal listed seven risks, and I have added one project management risk. I score each by likelihood (L) and impact (I) on a 1 to 5 scale, with an early trigger and a fallback. Risk matrices are standard, but Cox (2008, p. 497) shows they can "assign identical ratings to quantitatively very different risks" and can even rate smaller risks higher than larger ones. So I write a short reason beside each score and review the register weekly. Wingate (2025, p. 242) groups project risk into cost, schedule and technical risk, and notes that schedule risk can be handled with float in the schedule. With no budget at stake, my risks are mostly schedule and technical, which is why the plan keeps five days of slack and why most fallbacks protect a gate rather than a budget.
Scale. Likelihood: 1 = very unlikely, 3 = about even, 5 = more likely than not. Impact: 1 = a day lost, 3 = a week of slack used, 5 = blocks a gate or breaks a comparison; 2 and 4 sit between these. Any risk with L × I of 12 or more has its trigger checked at every weekly review; the rest are checked every other week.
| Risk | L | I | L × I | Reason for the score | Early trigger → fallback |
|---|---|---|---|---|---|
| Limited time alongside full-time work | 4 | 4 | 16 | Evenings and weekends only, in a seven-week window | One week behind the timeline, or advisor increment 2 not done by 9 Feb → cut the held-out advisor evaluation first |
| Vulnerability databases update between scans | 2 | 5 | 10 | Both update daily, but updates are switched off; one slip would break every comparison | Database date differs between the first and last scan → rescan all 15 in one serial run |
| Timing noise on the build server | 3 | 3 | 9 | The home server also runs other services | IQR above 10% of the median for any image → stop other services and redo its 10 builds |
| Files cannot be matched to a package | 3 | 5 | 15 | Copied native libraries and static binaries often have no package record | Pilot misses the planted library → fix the harness first; if still failing, narrow H2a to each native library, checked by hand |
| cve-bin-tool fails on a file | 3 | 3 | 9 | It only recognises products it has signatures for | No result for a file → record it as unknown, never as clean, and check it by hand (budget about 50 files, about 8 hours at 10 minutes each) |
| A hardened variant fails to build or run | 3 | 2 | 6 | Alpine (musl) and Distroless often break native dependencies | Build or smoke test fails → record it as a delivery cost; never drop it |
| A held-out Dockerfile cannot be converted | 3 | 2 | 6 | Random GitHub Dockerfiles vary widely | Not single-stage Python, Node.js or Go, or will not build as given → replace it with the next random pick and log why |
| Ethics approval takes longer than planned (new) | 2 | 4 | 8 | The approval window is 12 to 18 January, and approval is outside my control | No decision by 15 Jan → chase my supervisor, keep building (no data collected), and use the slack |
The weekly review is one standing card with five checks: milestones planned against done, any blocked cards, the evidence each upcoming gate needs, a revised forecast for the end date, and how much slack is left. Its notes go in the integrity log.
What I am leaving out
Week 2 also covered RACI charts, which assign roles across a team. On a solo project every row would say "me", so a RACI chart adds nothing. Instead I keep a short log of supervisor meetings and decisions.
References
- Ahmad, M.O., Dennehy, D., Conboy, K. and Oivo, M. (2018) 'Kanban in software engineering: a systematic mapping study', Journal of Systems and Software, 137, pp. 96-113. doi: 10.1016/j.jss.2017.11.045.
- Cox, L.A. (2008) 'What's wrong with risk matrices?', Risk Analysis, 28(2), pp. 497-512. doi: 10.1111/j.1539-6924.2008.01030.x.
- Phelps, R., Fisher, K. and Ellis, A. (2007) Organizing and managing your research: a practical guide for postgraduates. London: SAGE.
- Wilson, G., Bryan, J., Cranston, K., Kitzes, J., Nederbragt, L. and Teal, T.K. (2017) 'Good enough practices in scientific computing', PLoS Computational Biology, 13(6), e1005510. doi: 10.1371/journal.pcbi.1005510.
- Wingate, L.M. (2025) Project management for research and development: guiding innovation for positive R&D outcomes. 2nd edn. Boca Raton, FL: CRC Press.